A Validation Master Plan (VMP) describes how a whole site approaches validation. A Validation Plan (VP) describes how one project will be validated. They are often confused, and on some sites one document tries to do both jobs. That usually ends with a VMP that is out of date the week after a project finishes.
The Validation Master Plan: a site document
EU GMP Annex 15 expects the key elements of a site's qualification and validation programme to be defined and documented, typically in a VMP. In practice the VMP is a standing site procedure. It answers questions such as:
- What is the site's validation policy, and who is responsible for what?
- Which lifecycle approach do we use (URS, DQ, IQ, OQ, PQ, or a risk-based verification approach)?
- How do we decide whether a system has GMP impact?
- How are deviations, change control and periodic review handled?
- What systems are already validated, and when are they next due for review?
The VMP changes slowly. It is reviewed on a set cycle, usually every one to two years, and whenever the site's approach changes.
The Validation Plan: a project document
A Validation Plan is written at the start of a specific project: a new filling line, a building extension, a replacement autoclave, a new computerised system. It takes the rules in the VMP and applies them to that project. It answers:
- What is in scope, and what is not?
- Which systems need qualifying, and which only need commissioning?
- Which documents will be produced for each system, and who approves them?
- What are the acceptance criteria for the project as a whole?
- How will supplier documentation (FAT, SAT, turnover packages) be used?
- What does "finished" look like, and how will the project be closed out in a Validation Summary Report?
The VP lives for the life of the project. Once the summary report is approved, the VP is effectively closed.
How they connect
The simplest way to think of it: the VMP is the rulebook, the VP is the game plan for one match.
- The VMP should say that projects need a Validation Plan, and what one must contain.
- Each VP should reference the VMP and explain any project-specific departures from it.
- The VMP's system inventory should be updated when a project closes, so the newly validated systems appear with their report reference and next periodic review date.
Common mistakes
- Writing project detail into the VMP. Schedules, project teams and equipment lists date quickly. Keep them in the VP.
- No VP at all for small projects. A one-page VP for a single equipment replacement still makes scope and approvals clear before work starts.
- VMP and VP that disagree. If a project needs a different approach, say so in the VP and justify it. Don't quietly ignore the VMP.
- Forgetting the close-out. A project isn't finished until the summary report is approved and the VMP inventory is updated.