Validation Master Plan vs Validation Plan: what's the difference?

By Les Gilbert · 24 November 2026

A Validation Master Plan (VMP) describes how a whole site approaches validation. A Validation Plan (VP) describes how one project will be validated. They are often confused, and on some sites one document tries to do both jobs. That usually ends with a VMP that is out of date the week after a project finishes.

The Validation Master Plan: a site document

EU GMP Annex 15 expects the key elements of a site's qualification and validation programme to be defined and documented, typically in a VMP. In practice the VMP is a standing site procedure. It answers questions such as:

The VMP changes slowly. It is reviewed on a set cycle, usually every one to two years, and whenever the site's approach changes.

The Validation Plan: a project document

A Validation Plan is written at the start of a specific project: a new filling line, a building extension, a replacement autoclave, a new computerised system. It takes the rules in the VMP and applies them to that project. It answers:

The VP lives for the life of the project. Once the summary report is approved, the VP is effectively closed.

How they connect

The simplest way to think of it: the VMP is the rulebook, the VP is the game plan for one match.

Common mistakes