IQ, OQ and PQ are the three core stages of equipment qualification. Each answers a different question: is it installed correctly, does it work as specified, and does it do the job reliably in real use? Keeping those questions separate is the key to protocols that are quick to execute and easy to defend at inspection.
Installation Qualification (IQ): is it installed as designed?
IQ checks that the equipment delivered and installed matches the approved design and the manufacturer's recommendations. Typical IQ checks include:
- Equipment identity: make, model, serial numbers, against the purchase order and design.
- Materials of construction and surface finish for product-contact parts, with certificates.
- Utilities connected as specified: power, compressed air, water, steam, HVAC.
- Instruments installed, identified and calibrated, with certificates in date.
- Drawings (P&IDs, electrical) walked down and marked up as-built.
- Manuals, spares lists and software versions recorded.
IQ is largely static. If you find yourself running the equipment, you've probably moved into OQ.
Operational Qualification (OQ): does it work across its range?
OQ demonstrates that the equipment operates as intended across its specified operating ranges, including the limits. Typical OQ tests include:
- Functional tests of each operating mode and sequence.
- Alarms and interlocks: does each one trigger and respond correctly?
- Control loops and setpoints across the operating range, including upper and lower limits.
- Power failure and recovery.
- Computerised system functions: access levels, audit trail, data backup.
OQ is usually done without product, or with a placebo or water. Each test needs a clear, measurable acceptance criterion written before execution.
Performance Qualification (PQ): does it perform consistently in real use?
PQ shows that the equipment, with its utilities, procedures and trained operators, consistently performs as required under normal operating conditions. That often means product or a representative substitute, over several runs (three is a common minimum, but the number should be justified by risk).
For some systems, PQ overlaps with process validation. Make it clear in your Validation Plan where one ends and the other begins.
Writing good protocols
- Trace every test back to a requirement. If a test doesn't link to a URS or design requirement, ask why it's there. A traceability matrix makes this visible.
- Write acceptance criteria before you test. "Operates satisfactorily" isn't a criterion; "Temperature 121–124 °C at all probes for the full hold period" is.
- Don't repeat commissioning. Where commissioning or FAT/SAT tests were executed under good documentation practice and reviewed by Quality, reference them instead of re-running them.
- Plan for deviations. Something will fail. A clear deviation process in the protocol saves days.
- Record actual results, not ticks. Inspectors want to see the number that was measured.