Commissioning vs qualification: where one ends and the other begins

By Les Gilbert · 24 November 2026

Commissioning proves that a system has been built and works as engineering intended. Qualification proves, with Quality oversight, that it is fit for its GMP purpose. The two overlap heavily, and on many projects the same test is done twice: once by the contractor for commissioning, then again by the validation team for IQ or OQ. Getting the boundary right saves weeks.

What commissioning covers

Commissioning is a good engineering practice activity, usually led by engineering and the contractor. It brings a system from "mechanically complete" to "ready for use":

Commissioning applies to everything on a project, GMP or not: a car-park lighting system gets commissioned too.

What qualification adds

Qualification applies to systems with GMP impact. It is planned and approved under the site's quality system, typically through a Validation Plan and protocols approved by Quality. It focuses on the requirements that matter to product quality and patient safety, and it needs documented evidence that meets GMP standards.

Leveraging commissioning

The science- and risk-based approach set out in ASTM E2500 (current edition E2500-25) and the ISPE Baseline Guide on Commissioning and Qualification encourages using commissioning results as qualification evidence, instead of repeating tests. EU GMP Annex 15 also allows FAT and SAT results to be used, where appropriate and justified. For that to work:

  1. Decide early. The Validation Plan should say which commissioning tests will be leveraged into qualification.
  2. Agree the standard up front. Leveraged tests need pre-approved test scripts, clear acceptance criteria and good documentation practice, so contractors must know before they start.
  3. Involve Quality. Quality should approve the approach and review leveraged results, but needn't witness every commissioning test.
  4. Make it traceable. The traceability matrix should show which requirement was proven by which commissioning or qualification test.
  5. Handle failures properly. A failure in a leveraged test needs recording and resolving, just as in a protocol.

Where projects go wrong

A note on what's changing

Annex 15 dates from 2015. In 2026 the EMA and PIC/S published a concept paper on a targeted revision, mainly to extend it to active substance manufacturers and align it with ICH Q9(R1) on quality risk management. The principles above are unlikely to change, but keep an eye on the draft when it appears.